Commissioning a piece/7 min read
How long custom furniture takes in Adelaide
Book a Christmas table in September and you will not get it. Adelaide workshops fill their December slots by about August. Here are the real timeframes.

Ready to price something specific? See dining tables in Adelaide or bedheads in Adelaide.
Custom furniture in Adelaide takes 4 to 16 weeks from deposit to delivery, depending entirely on what the piece is. A bedhead runs 4 to 8 weeks, a dining table 8 to 14, and a fitted joinery run 8 to 16. Roughly half of any of those numbers is time your job spends waiting in a queue, which is the part almost nobody accounts for.
Realistic lead times by piece
These are total times from paid deposit to delivered piece, split into the 2 components that make them up.
| Piece | Total lead time | Queue | Time at the bench | | --- | --- | --- | --- | | Bedhead | 4 to 8 weeks | 2 to 5 weeks | 2 to 3 weeks | | Coffee table | 5 to 9 weeks | 3 to 6 weeks | 2 to 3 weeks | | Shelving or bookcase | 5 to 10 weeks | 3 to 6 weeks | 2 to 4 weeks | | Desk | 6 to 10 weeks | 3 to 6 weeks | 3 to 4 weeks | | Entertainment unit | 6 to 11 weeks | 3 to 6 weeks | 3 to 5 weeks | | Built-in wardrobe | 6 to 12 weeks | 3 to 6 weeks | 3 to 6 weeks | | Outdoor setting | 7 to 12 weeks | 4 to 7 weeks | 3 to 5 weeks | | Buffet or sideboard | 8 to 13 weeks | 4 to 7 weeks | 4 to 6 weeks | | Dining table | 8 to 14 weeks | 4 to 8 weeks | 4 to 6 weeks | | Fitted joinery run | 8 to 16 weeks | 4 to 8 weeks | 4 to 8 weeks |
Add 1 to 3 weeks in front of all of these for the design stage, which happens before the deposit. That is covered in how commissioning actually works, and it is the stage most likely to eat time you did not budget for.
Queue time and bench time are 2 different numbers
This is the distinction that makes every other number on this page make sense, and it is worth asking your maker to separate them.
Bench time is the hours your piece is actually being worked on, spread over the days that work has to sit. A dining table is roughly 35 to 50 hours of labour, but it cannot be compressed into a week. Timber has to sit after milling before it is jointed. Glue-ups need overnight clamping. A finish needs 3 to 5 coats with real cure time between each, and in a workshop under 15 degrees through an Adelaide winter that cure time can double. The 4 to 6 weeks on a table is not slack: it is the physics of the material.
Queue time is the weeks before your job reaches the bench at all. It is set entirely by how many jobs are booked ahead of you, and it moves every week you delay paying your deposit.
Shortening the total therefore has exactly 1 reliable lever: order earlier. Asking for a rush shortens bench time, and shortening bench time means fewer finish coats or less cure, which is the wrong saving on a piece you intend to keep for 30 years.
Why the queue dominates in Adelaide
The Adelaide custom furniture market is made up of small independent workshops, most of them 1 to 3 people. That is not a criticism, it is the structure of the trade here, and it has 2 direct consequences for your timeline.
There is no second bench. In a 20 person joinery factory a job can be moved sideways to whoever is free. In a 2 person shop the jobs run in sequence, and a job that overruns pushes everything behind it. A 1 week overrun on the job in front of yours is a 1 week slip on yours, and there is nothing anyone can do about it.
The queue also fluctuates hard. A single 6 week kitchen booked in March can be the reason a bedhead quoted at 5 weeks in February is quoted at 9 weeks in April. Ask what the current queue is rather than what the standard lead time is, because they are frequently different numbers.
The December problem
This is the single most predictable timing failure in the Adelaide market, and it happens every year.
Demand for dining tables, outdoor settings and buffets concentrates on Christmas. Workshops fill their December delivery slots by about August. Most then close for 2 to 3 weeks from mid-December, and January is slow to restart because timber suppliers and hardware distributors close too. The practical effect is that a job not booked by late winter does not get delivered before Christmas, it gets delivered in February.
Count backwards to find your order date.
| Want it for | Piece | Lead time | Order by | | --- | --- | --- | --- | | 20 December | Dining table | 8 to 14 weeks plus buffer | End of July | | 20 December | Outdoor setting | 7 to 12 weeks plus buffer | Early August | | 20 December | Buffet or sideboard | 8 to 13 weeks plus buffer | End of July | | 20 December | Bedhead | 4 to 8 weeks plus buffer | Mid October | | End of school holidays, late January | Fitted joinery | 8 to 16 weeks plus buffer | Mid September |
The buffer in that table is 2 to 3 weeks and it is not optional in the last quarter of the year. Check the South Australian public holiday dates against your delivery window too, because a fitted install that lands across a long weekend loses more days than the holiday itself.
The reverse of this is worth knowing: February to May is the quietest ordering window in Adelaide, and a table ordered in March frequently arrives at the short end of its band.
What legitimately causes a slip, and what does not
Legitimate:
- Timber supply. Tasmanian oak and Victorian ash arrive through the eastern states. A pack that comes in short on grade costs 2 to 3 weeks while another is sourced. Wider boards and figured stock are worse.
- A customer decision. A species change, a size change or an unreturned drawing approval. The clock does not run while a maker is waiting on you.
- A site measure that finds a problem. An out-of-square wall, a floor that falls 25mm, a wall with no stud where a rail needs one. Better found at week 2 than week 12.
- Weather. A run of cold, damp weeks genuinely slows finishing, and a maker who waits for a coat to cure properly is doing the right thing.
Not legitimate:
- No revised date offered, or a date that moves a second time without explanation
- A slip discovered because you asked, rather than because you were told
- A "nearly finished" that stays nearly finished for 3 weeks
A 1 to 2 week slip on a 12 week job is normal. Past 4 weeks with no clear cause, you are entitled to a written revised completion date, and Australian Consumer Law consumer guarantees include that services be supplied within a reasonable time.
How to hit a hard deadline
If the date is genuinely fixed, a wedding, a move-in, a Christmas, do these 5 things.
- Order at the long end of the band, plus 3 weeks. For a dining table, that means starting 17 weeks out, not 8. Have the size settled before you start, using the clearance rules, because a size change after the timber is bought is a new order rather than an amendment.
- Say the date is hard in your first email, and ask the maker to confirm it in writing against their current queue rather than their standard lead time.
- Settle timber and finish before the drawing. This is the decision that stalls jobs, and it is entirely inside your control. Compare species in the timber guide while you are waiting on quotes.
- Return approvals inside 48 hours. Every day you hold a drawing is a day added to the far end.
- Keep the buffer to yourself. A maker given a date 3 weeks early will work to it. A maker told about the buffer will work to the real date.
Send a complete brief up front so nothing stops at stage 1. There is a copyable one in how to brief a furniture maker, and it takes 5 minutes.
Timing questions are piece-specific, so the detail lives on the piece pages: custom dining tables runs 8 to 14 weeks and is the category most affected by December, while custom bedheads at 4 to 8 weeks is the piece most likely to still be achievable at short notice.